Project Aurora
Relaunch of the flagship monthly, covering the redesign, the print partner and the subscriber delivery experience.
Current status
Print Aurora with Calder Print
Why
The trial run reached subscribers roughly four days sooner than Halstead on an identical schedule, with no colour drift complaints and no change in cost per copy once carriage is included.
Open commitments
- Tom Blake, Send the Leeds folding line timeline in writing37 days overdue
- You, Send Sarah the revised relaunch plan with the new datesDue tomorrow
- You, Write and circulate the one page Calder rationaleDue Tuesday
- Daniel Okafor, Sign off the reconciled Calder cost per copy modelDue Wednesday
- Sarah Thompson, Send updated copy deadlines for the three changeover issuesDue Friday
- Mike Adeyemi, Document the fallback procedure for each changeover issueDue 7 Sep
Recent decisions
Print Aurora with Calder Print
Because Roughly four days faster to the doorstep across two independent runs, no colour drift against Halstead's four flagged runs, and commercially near neutral once carriage is included.
27 Aug
Change over across three issues, supplements first
Because Each stage keeps a fallback to Halstead, limiting the risk to any one issue.
24 Aug
No printer change without a one page rationale for Marcus
Because Publisher approval requires a concise, evidence backed case.
10 Aug
Measure the full press to doorstep timeline before judging the printer
Because Opinion was outrunning evidence; no printer decision without measurement.
17 Jul
Timeline
15 Jul
Halstead was the preferred printer at renewal on cost and familiarity; late arrivals were logged as a watch item, not a blocker.
15 Jul
Stay with Halstead for now, Cost advantage and low changeover risk; late arrivals treated as a watch item.
17 Jul
Aurora began as a measurement exercise: no printer judgement until the full press to doorstep timeline was measured.
17 Jul
Measure the full press to doorstep timeline before judging the printer, Opinion was outrunning evidence; no printer decision without measurement.
21 Jul
Tom Blake acknowledged the late arrivals and promised a Leeds folding line fix, the third such promise in 2026.
3 Aug
The printer position shifted from watch item to active problem when average arrival moved from 10.8 to 12.1 days while awaiting their fix.
6 Aug
Calder Print offered a full trial print run of the September issue with no commitment.
10 Aug
Marcus will approve a printer change only with measured evidence and a one page rationale.
10 Aug
No printer change without a one page rationale for Marcus, Publisher approval requires a concise, evidence backed case.
20 Aug
Print quality: Halstead had four runs this year with cover colour drift; Calder had none across the trial.
20 Aug
Trial result: Halstead averaged 12.4 days to the doorstep against Calder's 8.2, roughly four days in Calder's favour.
20 Aug
Sarah asked whether a single trial issue is representative enough to sign against.
21 Aug
Cost model: Calder is 3 per cent higher on list price but roughly neutral once carriage and proofing rounds are included.
24 Aug
Changeover sequenced across three issues, supplements first, with a fallback to Halstead at each stage, about six weeks of production attention.
24 Aug
Change over across three issues, supplements first, Each stage keeps a fallback to Halstead, limiting the risk to any one issue.
26 Aug
The trial numbers held on the second run, removing the main objection to the decision.
27 Aug
Team agreed to print Aurora with Calder, subject to cost model sign off and a contractual delivery clause.
27 Aug
Printer position over time: Halstead preferred in July, late arrivals escalate in early August, Calder trialled on 20 August, Calder selected on 27 August.
27 Aug
John is the brake on changing printer: he moved only once the commercial gap closed to near neutral.
27 Aug
Print Aurora with Calder Print, Roughly four days faster to the doorstep across two independent runs, no colour drift against Halstead's four flagged runs, and commercially near neutral once carriage is included.
28 Aug
Open question: can the supplements move to Calder before the contract is countersigned?
28 Aug
Sarah owes you updated copy deadlines for the three changeover issues.
28 Aug
You committed to sending Sarah the revised relaunch plan with the new dates by Friday.
28 Aug
Recurring topics with Sarah: the printer changeover, delivery times, contract timing and editorial capacity.
28 Aug
Sarah consistently reasons from measurement and reacts badly to timeline promises without numbers behind them.
Conversations
- 28 Aug, Relaunch planning discussion
- 27 Aug, Aurora decision review
- 26 Aug, Delivery catch-up
- 24 Aug, Changeover sequencing
- 21 Aug, Cost per copy review
- 20 Aug, Calder trial run results
- 10 Aug, Aurora risk review
- 6 Aug, Calder Print introduction
- 3 Aug, Late issues escalate
- 28 Jul, Weekly Aurora sync
- 21 Jul, Halstead quarterly review
- 17 Jul, Project Aurora kickoff
- 15 Jul, Print partner review