Before we get into the schedule, I want to talk about arrival dates. We raised it in April, we raised it in May, and it has got worse.
00:14
Tom Blake
I understand the frustration. The bindery capacity work is scheduled, we are looking at completion within the quarter.
00:38
Alex Rivers
That is the same commitment I was given last quarter. What is different this time?
00:52
Tom Blake
The difference is the second folding line in Leeds is now funded. It was not funded when we last spoke.
01:19
Alex Rivers
And if it slips again? We have a renewal decision to make and I cannot keep asking editorial to absorb this.
01:36
Tom Blake
I would ask you not to make a renewal decision on a single measure. Our print quality record is strong.
02:04
Alex Rivers
Quality is not the problem. The problem is that subscribers read the issue after they have seen it on the newsstand.
02:22
Tom Blake
Understood. I will send you the Leeds timeline in writing by the end of the week.